Which of the following types of information is shared between Teams of the ART?

Get ready for the SAFe Product Owner/Product Manager (POPM) Certification Test. Study with flashcards and multiple choice questions, with detailed hints and explanations. Boost your confidence and pass with ease!

In the context of Agile Release Trains (ART) in the SAFe framework, sharing a single backlog among teams is a key aspect that promotes alignment, transparency, and shared responsibilities. When teams operate off a single backlog, it allows for coordinated planning and prioritization of work. This ensures that all team members are aware of the same objectives, fostering collaboration and facilitating better decision-making across the ART.

The single backlog helps in managing dependencies effectively, as teams can see what other teams are working on and adjust their work in response, improving overall flow and reducing bottlenecks. Having this unified view also aids the Product Owner in communicating priorities and maintaining a consistent product vision.

In contrast, while commitment to agility, a set of metrics, and a set of regulations are important to the functioning of teams and the ART, they do not represent shared information in the same formalized manner. Commitments to agility reflect a mindset rather than a concrete artifact shared among teams. Metrics might be used internally within teams or across the ART, but they do not coalesce into a single item like a backlog does. Regulations might guide behavior and practice but are typically not shared as a common resource like a backlog, which serves as the focal point for development work across the ART

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy