Which statement is true about Weighted Shortest Job First?

Get ready for the SAFe Product Owner/Product Manager (POPM) Certification Test. Study with flashcards and multiple choice questions, with detailed hints and explanations. Boost your confidence and pass with ease!

Weighted Shortest Job First (WSJF) is a prioritization technique used in the Scaled Agile Framework (SAFe) that helps teams determine the order in which to work on features and capabilities. The correct response highlights that WSJF considers both the cost of delay and job size.

The cost of delay quantifies the potential impact on value or benefits if the job is delayed, while job size refers to the effort required to complete the task. By combining these two elements, WSJF enables teams to prioritize work that delivers the highest economic value in the shortest possible time. This holistic view allows for more informed decision-making regarding which tasks will have the most significant impact on business objectives when completed sooner rather than later.

In contrast, other choices emphasize narrower aspects of task prioritization. For example, one option suggests that job size alone is the sole consideration, which overlooks the critical economic aspect introduced by the cost of delay. Another option implies that prioritization is based on team preference, which does not align with the structured, value-driven approach of WSJF. Lastly, one option indicates that WSJF is primarily focused on scheduling, which misses the key economic factors that guide the prioritization process. Overall, the combination of cost of delay and job size

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy