Which tool shows dependencies during PI Planning?

Get ready for the SAFe Product Owner/Product Manager (POPM) Certification Test. Study with flashcards and multiple choice questions, with detailed hints and explanations. Boost your confidence and pass with ease!

The ART planning board is the essential tool used during PI Planning to visualize and manage dependencies among teams within the Agile Release Train (ART). This board allows teams to outline their iterations and planned work, facilitating a clear understanding of how their deliverables impact each other.

By utilizing the ART planning board, teams can identify and address any inter-team dependencies that may create risks to achieving their objectives. This shared visibility supports collaboration and a collective approach to planning, ensuring that all teams are aligned and aware of how their work integrates into the broader program goals.

In contrast, while other tools like the risks board serve to identify potential risks and objectives convey what each team aims to achieve, the ART planning board specifically emphasizes the visual tracking of dependencies that are critical for the successful coordination of efforts across multiple teams during PI Planning.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy